Retention requirement changes

The Queensland Building and Construction Commission Act 1991 (QBCC Act) provides for requirements for retention monies.

The Building Industry Fairness (Security of Payment) Act 2017 (BIF Act) made changes to the QBCC Act around retentions and securities withheld under a contract, and defects liability periods.

The changes strengthen and protect the rights of contractors where a retention is withheld. They commenced on 17 December 2018.

The new requirements apply to:

  • all existing building contracts
  • any building contracts entered into from 17 December 2018.

See more details in Part 4A of the QBCC Act.

On this page:

Statutory defects liability period

At the end of the defects liability period, retention monies can no longer be retained to fix defects in the building work. Previously it wasn’t always clear when a contractor was entitled to claim and be paid retention.

A new statutory defects liability period of 12 months from the date of practical completion will apply if a contract doesn’t provide for one.

The statutory defects liability period applies only if the building contract doesn’t state an identifiable period for releasing retentions (e.g. a defects liability period).

This applies to any existing contract where a retention amount is still being held and practical completion hasn’t been reached.

No practical completion date stated

The practical completion date is usually stated in a contract.

The QBCC Act provides a definition for practical completion that can be used to calculate the relevant date when the 12 months defects liability period commenced.

If the contract doesn’t provide a date or time frame for work completion, practical completion is the day the work is completed in compliance with the contract, including all work plans and specifications, and all statutory requirements applying to the work, without any defects or omissions (see section 67A of the QBCC Act).

Defects liability period for existing contracts

New section 67NA can apply to an existing contract if both the:

  • practical completion occurred before 17 December 2018
  • the 12-month statutory defects liability period results in the end date falling on or after 17 December 2018.

It doesn’t apply if practical completion was more than 12 months before 17 December 2018.

See where the statutory defects liability period does and doesn’t apply:

Contract/building work is in construction phase - practical completion hasn’t passed

A defects liability period of 12 months applies starting on the future day of practical completion.

Contract or building work is in defects liability period - practical completion passed less than 12 months earlier

The defects liability period of 12 months applies backdated to start from the already passed day of practical completion.

Contract or building work has passed the statutory defects liability period - practical completion passed more than 12 months earlier

The 12-month defects liability period does not apply to this contract.

Notification of defects liability period ending

The party withholding retentions or securities under a building contract (excluding principals) must notify the party they’re withholding the amounts from within 10 business days of the defects liability period ending (or within 5 business days after receiving notice if the defects liability period is linked to another building contract).

The requirement applies only if the end of the defects liability period is at least 10 business days after 17 December 2018 (i.e. it doesn’t apply if the period ended before 4 January 2019 because a contracted party would’ve had to give a notice before the requirement commenced).

The notice requirements don’t apply retrospectively; however, if a party is holding a retention amount for a historic or completed contract, the party may use a S67NC Notice of end of defect liability period (PDF, 40KB) to remind contractors of their right to make a payment claim.

Penalty for not releasing retention amounts

A maximum penalty of 200 penalty units or one year’s imprisonment may apply for failing to release a retention amount to the contracted party in accordance to the contract without a reasonable excuse.

The penalty will not apply retrospectively to retentions that were due to be paid before commencement, i.e. existing contracts. It will apply only where the due date is after commencement – 17 December 2018.

So regardless of when the defects liability period ended or the final payment claim was received, if the due date when the retentions should’ve been paid is after 17 December 2018, the penalty may apply.

When retentions must be paid

The party holding retention monies must release them according to the building contract unless they have a reasonable excuse. A contractor isn’t required to pay retentions immediately when the defects liability period expires. The ‘due date’ for payment under the building contract is the required release date.

The new penalty provision applies to any retention amount withheld under a building contract, not just a final retention.

Therefore, if the contract specifies the release of part of the retention amount at practical completion or any other time, a penalty may apply for failing to do so without reasonable excuse.

Working out the due date

Contract provisions and other payment claim provisions of the BIF Act (see sections 73 and 75) are used to work out the due date for paying a retention amount.

If the contract has a specific retention release date, this is the date the retention will need to be paid.

If the building contract requires a contracted party to make a ‘final payment claim’ for any withheld retention amount at the end of the defects liability period, the ‘due date’ for paying the retention will be in accordance with the agreed payment terms (e.g. 25 business days from receipt of the payment claim).

If a contract doesn’t provide for making a final payment claim, section 75(3) of the BIF Act applies: a final payment claim must be provided within 28 days after the end of the last defects liability period.

Contractors should ensure they make a ‘final payment claim’ within the required timeframe, otherwise they may not be able to make a valid claim their retentions at a later date. New section 67NC will remind contractors that the defects liability period is ending. If a final payment claim for retention amounts isn’t provided in the required time frame, the payment claim may be invalid.

The BIF Act doesn’t prevent a contractor releasing retentions earlier and/or without a payment claim if they believe the full amount is payable (i.e. there are no defects to correct).

What is a reasonable excuse

As retention amounts are held to cover the cost of correcting building work defects or secure the contract performance, a reasonable claim on retentions would need to relate to these matters.

For example, defective or incomplete work is the contracted party’s responsibility if the contract allows the use of retention monies in that instance.

The QBCC Act allows retentions to be withheld to the extent that they’re the subject of a dispute or a subcontractor’s charge.​​​



Last updated 20 February 2019    Creative Commons Attribution 4.0 International (CC BY 4.0)


Copyright |  Disclaimer |  Privacy |  Right to information |  Accessibility |  Jobs in Queensland |  Other languages

© The State of Queensland – Department of Housing and Public Works 2009–2019

Queensland Government