About the project

The Department of Housing and Public Works is leading the delivery of the North Queensland Stadium project, which is expected to support up to 750 jobs throughout the design and construction stages.

The project provides a catalyst for urban regeneration in Townsville, attracting further investment into the region and supporting jobs growth.

Once complete, the stadium will host a multitude of sporting, cultural and community events.

North Queensland Stadium is a joint project of the Queensland Government, Australian Government and Townsville City Council, and is supported by both the National Rugby League and the North Queensland Cowboys. The stadium forms part of the Townsville City Deal signed in December 2016.

Vision

The project vision is to develop a vibrant new multi-purpose stadium that:

  • attracts visitors and investment
  • celebrates Townsville's tropical climate
  • values the water-edge environment
  • delivers high quality public spaces
  • supports urban regeneration.

Objectives

The project objectives are:

  • deliver a new best-practice, multi-purpose, regional stadium in Townsville by the commencement of the 2020 National Rugby League Premiership Season
  • maximise employment and business opportunities for the people of Townsville and the North Queensland region.

Benef​​its

The North Queensland Stadium project is anticipated to be a catalyst directly and indirectly stimulating change that will benefit Townsville and the North Queensland region.

These changes include:

Expanding North Queensland infrastructure

  • providing a nationally-recognised stadium with a uniquely 'North Queensland' identity, that draws on world class design and architecture.

Supporting jobs and flow-on economic benefits

  • supporting initial regional employment and supply chain investment during design and construction, and future opportunities when the facility is operational
  • attracting broader investment and economic development to Townsville in the long term, as a major regional city supporting further job growth.

Fostering urban regeneration and enhanced liveability

  • transforming and activating places and spaces as an urban attraction that draws people to Townsville's city heart
  • promoting active experiences and social interaction including a broad range of sporting, community and cultural activities.

Raising the profile of North Queensland region

  • attracting investment underpinned by sporting excellence, events capability, distinct tourism offerings for domestic and international visitors, and strong and diverse local economies.

Timeline

The North Queensland Stadium project is on schedule to be completed in time for the start of the 2020 National Rugby League (NRL) Premiership season.

Early works have been completed and the build of the main superstructure is now underway.

Project milestones

These dates are subject to inclement weather events, latent site conditions and other unforeseen issues.

Item

Date​

Schematic Design completed

23 August 2017

Development Design completed

8 December 2017

Main stadium build commenced

1 May 2018

Stadium complete

Early 2020

Project delivery team

The delivery of the North Queensland Stadium project is being led by the Department of Housing and Public Works with an experienced team of contractors and consultants including:

  • Managing Contractor: Watpac
  • Principal Consultant: Cox Architecture
  • Audit Quantity Surveyor: AECOM
  • Audit Programmer: RCP.

Location

The North Queensland Stadium site is located within the Townsville City Waterfront Priority Development Area adjacent to the Townsville Central Business District, between Ross Creek and Saunders Street.

View a map of the North Queensland Stadium site​.

Stakeholder engagement and communication

The Government is committed to continuing to work closely with our project partners and stakeholders throughout the design and construction of the North Queensland Stadium.

Information about the project and its progress will be regularly shared here.

General enquiries about the project should be directed to the Department of Housing and Public Works: BPAMprojectdelivery@hpw.qld.gov.au​.

 

Enquiries about construction activities on site should be directed to Watpac: nqstadium@watpac.com.au.​​​​



Last updated 30 January 2019    Creative Commons Attribution 4.0 International (CC BY 4.0)


Copyright |  Disclaimer |  Privacy |  Right to information |  Accessibility |  Jobs in Queensland |  Other languages

© The State of Queensland – Department of Housing and Public Works 2009–2019

Queensland Government