View Contract Details

Walking track construction for Trail A, Curtis Island National Park.  

Department of Environment and Science
Level 32, 400 George Street, Brisbane, QLD, Australia, 4000
DES18190
Walking track construction for Trail A, Curtis Island National Park. (DES18190)
Works
Walking track construction for Trail A, Curtis Island National Park.

The project requires the Construction of approximately 4.2km of new track works as detailed on the plans and specifications provided. The work involves excavation/ cutting in the new works to gain machinery access; carting and placement of materials construction of steps and drains; finalising the track pavement to finished surface; and tidying and rehabilitating the site.

Complete requirements are outlined in the following documents:

Attachment No.

Name of Document

Description

2

Medium Works Conditions

Tender and Contract conditions, Annexure and Schedules

3

Project Brief

Scope of work

 

The Department is currently in progress of finalising the further construction of trails B, C and D. It is at the Departments absolute discretion to request the Supplier to provide a written offer for the continued construction of multi-use trails on Curtis Island (Trail B, C and D), once The Department has finalised the design utilising the same Terms and Conditions of Contract.

This would be at the Departments absolute discretion and depending on the following:

·         The design for Trails B, C and D being finalised before the Supplier has demobilised from site at completion of Trail A;

·         The Successful Supplier has identified its willingness and capacity to undertake the Stage 2 works (refer to Response Form 5.4 in this RFQ);

·         The Customer’s requirements have been satisfactorily met through Trail A works (taking into consideration the KPIs in Project Brief in Attachment 3);

·         The Supplier and the Department can agree on the price and timeframe for Trails B, C and D. 

 

Note: The first three (3) dependencies above would have to be meet for the Department at its absolute discretion to request the Supplier to provide a written offer for the Stage 2 Project.

An award (variation to contract) for the further 3 trails to the Supplier would require all the above dependencies being meet.

The Department in its absolute discretion may complete a separate tender process for trails B, C and D.

For detailed information on the specific goods / services sought under this tender, please review the "Specification Documents" in "Section 3 - Here is the detail".

20 May, 2019
Building and Construction and Maintenance Services - (100%)
open offer process
No
$139,370 (Estimate)
Rockhampton
Gladstone
Wide Bay Burnett
25 Jun, 2019
26 Jun, 2019
7 Aug, 2019
7
Michael Melit
OFFICE: (07) 33306252
michael.melit@des.qld.gov.au

Contractors

Fiddlers Green Landscaping
PO Box 548, Cannonvale, QLD, Australia, 4802
Price: $ 139370.00